In Which Some Minor Electrical Work is Performed
----Super late post is super late. Sorry.----
The Problem
The Plan
- Add support for a 240V 40A induction cooktop to replace the gas cooktop
- Add (not move) a laundry circuit to the first floor of the house (120V 20A and 240V 30A)
- Add a subpanel to the garage for outbuilding isolation and future welder/compressor needs
- Add a subpanel to the basement and move all the basement appliances and circuits for future simplicity and the addition of 240V 30A table saw/dust collector circuits
- Open up space on the overfilled main panel: all 20 spaces were filled and only 2 breakers were not tandems (including the 240V breakers)
- remove as much of the old rag-wire NM cable as possible (for my peace of mind)
- eliminate all k&t wiring
The Fix
Once the work started, I had no complaints. Yeah, it took longer than they thought it would, but I had my suspicions that they didn't know what they were getting into in the crawlspace and I'm honestly just glad it wasn't me down there. One complication that we found a really good solution for was the feed to the garage subpanel: there was already a 2" conduit that ran right from the garage, under the breezeway, and terminated just inside the addition foundation crawlspace that was perfect for the feeder conduit needed to support the 100A subpanel. The problem is that the conduit went below grade, so the conductors had to be below grade rated (makes sense), but the conductors (individual insulated wires for each leg+neutral+ground) aren't rated for running inside the house and crawlspace, so they had to be terminated and connected to Aluminium SE-R cable somewhere in close proximity to the house-end of the conduit. Their original plan was to mount a big ol'e junction box above one of the crawlspace vents, but I pointed out that they could mount the box inside the kitchen closet, which just happened to be right above the conduit termination point: perfect. (BTW, this is why you should always pay attention and make sure you know what the heck is happening when contractors are working on your house)
Another problem they ran into was the way the addition foundation was poured/built: for some reason (likely because they needed undisturbed grade) the addition concrete foundation wall was poured a yard away and parallel to the existing foundation wall with a small man sized opening to access the space in between. Apparently, once you entered the lobster trap, you couldn't actually see the exit or even any light from the crawlspace vents. Yikes, can you say confined space! better hope your flashlight doesn't run out of power while you're down there... I think the close quarters added a couple of hours to the project alone, although waiting for the crawlspace guy to show up 3 hours late while the primary electrician tried to keep busy didn't help either.
After the first 2 days of scheduled work were complete, they ran into scheduling issues and weren't sure when they could return to finish the job. Too bad we all (me included) forgot that the water heater was disconnected when the basement subpanel was installed and never reconnected. Oops. Luckily, the electrician managed to open his afternoon and came by for what would be many late evenings of trying to get my house completed.
Other than that, the project took as long as it took. I got my laundry room and my subpanels (still wish I had insisted on 100A in the basement, though I have no idea how they would've managed to run the size conductors they would've needed, 6 AWG was hard enough) and the basement is now wired with romex. The subpanels make adding additional circuits super easy and limit my chance of frying myself since I can shut off the feed to the entire subpanel from the main panel.
Doug, the electrician, was great. As I mentioned, I have no problem with how long it took once the work actually started (and it's unlikely that the owner is going to be getting surprised married again anytime soon).
Comments
Post a Comment